Business and Release Readiness: when is the right time to start planning what needs to be assessed?

Posted by Prue Beams on April 1, 2019

The competing demands and stress leading up to go-live can leave any good project manager wondering ‘what have we forgotten?’  It is not unusual for a go-live decision to be based on compromises and an acceptance of a certain amount of risk.  But what can be done leading up to this point to assess how ready an organisation is for the change and to address any business or technical readiness gaps?

Validating Business and Release Readiness is a vital activity in the final delivery stages of IT change programmes.  A Readiness Assessment is applicable not only when implementing a new Student Information System (SIS), but also when deploying a point solution, a new release or transitioning across to cloud-based modules. The readiness assessment may not be 100% complete until right before go-live, but the planning of what needs to be assessed starts well before this to ensure there is time to address any gaps. And as implementation is at the heart of what we do here at Tribal, we’ve worked with customers to develop a ‘readiness validation’ tool to help identify any gaps and assess their readiness ahead of go-live.

The Business and Release Readiness validation tool covers all the technical elements required to release the new solution, as well as all the business elements required for successful change management.  Ultimately owned by the Project Manager, other key project members like the Change and Release Managers can also track their progress and deliverables in this tool, as summarised here:

Release Readiness – being technically ready

There are 15 categories with over 160 assessment items to review and track Release Readiness, which requires input from the Release Manager, Technical Lead, Product Owner, Test Manager and of course the Project Manager.

With such a large scope of activities that need to be completed, without this systematic process or tool, the Project Manager will inevitably open themselves up to the risk of some areas not being fully assessed. From a governance perspective there also needs to be adequate tracking in place to enable informed decisions on proceeding with the go-live.

Business Readiness – focusing on the people side of change

To ensure all the right building blocks for successful change management are in place, Business Readiness validation is typically completed by the Change Manager, Training Manager and Communications Lead.

Key activities like Change Impact Assessments and Change Readiness Assessments will feed into the tool, along with the development of a detailed go-live communications plan.  In validating business process changes it is not unusual to uncover areas of the business that had not be considered, or where the full impact was not completely understood by stakeholders.  Interim processes may need to be developed to fill any go-live gaps, and in-flight processes will need to be identified to articulate how information will be captured during the freeze period and entered into the new system after go-live.  This alongside detailed documentation and training activities makes up the key categories within the tool.

New call-to-actionSo how does the readiness validation tool work?

The readiness validation tool identifies high-level categories that contain detailed criteria to be assessed.  Each category is assigned an owner who will be required to identify:

  • appropriate sign-off criteria
  • evidence and/or a deliverable
  • who is responsible for signing it off and by when
  • a risk rating – meaning criteria can be weighted in terms of potential impact on go-live
  • an ongoing assessment of the readiness status of the item – whether items are currently absent, not validated, conditionally validated, or signed-off.

As the tool tracks progress through a set of statuses, it is useful to complete an initial review at the start of the delivery phase.  It is completely reasonable that items may not be validated at this stage, but if criteria are currently absent from the delivery plan, then steps to address these gaps need to be swiftly put into place.

Used effectively, this Business and Release Readiness validation tool is proven to:

  • save time – it comes with pre-populated categories and criteria based on industry best practice
  • give earlier oversight of potential gaps and risks to go-live
  • give assurance that all items have been reviewed
  • present accurate information to governance groups to enable a go-live decision
  • help the Project Manager understand who needs to know what and when.

In our next blog we’ll discuss one of the most critical items within the Business and Release Readiness tool – gaining buy-in to develop an effective Operational Support Model for BAU.Click here get in touch with one of  our Professional Services team

Topics: Higher Education

Picture of Prue Beams

Written by Prue Beams

In 2014 Prue joined Tribal’s recently formalised Transformation and Change team. Prue comes to Tribal with a proven background in delivering business transformation and change management for public and private sector clients’ across NZ, Australia and the UK. She is a pragmatic and results-driven consultant/change manager, specialising in designing and implementing strategic transformations such as system implementations, operating model/ organisation design, process improvement and cost reduction projects. Prue has had exposure to a wide range of change management and consultancy methodologies and works closely with clients to tailor an approach most suited to their needs.